Fast facts:
- The $4.1 million investment includes rebuilding the M-343 (Gull Road) intersections at G Avenue, 27th Street and 28th Street.
- Work is expected to begin March 22 and be open to traffic by Aug. 1.
- The project and detours are explained in an MDOT YouTube video.
- Pre-work: 28th St. Intersection and M-343, 3/22 – 4/24
- Stage 1: MOT Bypass and Widening, 4/24 – 5/11
- Stage 2: G Ave. and Roundabout, 5/8 – 7/7
- Stage 3: Roundabout Completion, 7/3 – 7/24
- Stage 4: Temporary Pavement Removal and Restoration, 7/24 – 7/30